BATTLE CREEK, MI (WNWN/WTVB) – There has been a change in the schedule for the rebuilding of the Capital Avenue bridge over I-94 in Battle Creek.
While it is still is expected to be completed by September 23, the Michigan Department of Transportation says the closure is being extended one week to September 30 in order to rebuild the westbound I-94 ramps.
The original schedule would have seen one lane of Capital Avenue reopen in each direction on September 23 with the westbound ramps closed for an additional six to eight weeks for rebuilding.
MDOT officials say by extending the Capital Avenue closure one week, the contractor is planning to rebuild the westbound ramps in two weeks, starting next Monday, September 18.
Work to rebuild the westbound ramps is expected to be completed Saturday, September 30.
———————————-
The following detours will be posted for Capital Avenue:
Northbound traffic will be detoured on eastbound Beckley Road, northbound I-194/M-66, and westbound M-96 (Columbia Avenue).
Southbound traffic will be detoured on westbound Knapp Drive, northbound Minges Road, westbound Watkins Road, southbound Helmer Road, and eastbound I-94.
The following ramp detours will be in place:
The westbound I-94 ramp to northbound Capital Avenue will be detoured on northbound I-194/M-66 and westbound M-96 (Columbia Avenue).
The westbound I-94 ramp to southbound Capital Avenue will be detoured on southbound I-194/M-66 to westbound Beckley Road.
The Capital Avenue ramp to westbound I-94 will be detoured on westbound Knapp Drive, northbound Minges Road, westbound Watkins Road, and southbound Helmer Road.
This work is part of MDOT’s three-year, $160 million project to repave 10 miles of I-94 between Helmer Road and 17 1/2 Mile Road. They are also rebuilding nine bridges while repairing six others.